| WEEK |
 |
GLW |
GLE |
MEYER |
OTHER FACIL. |
OPERATIONAL |
 |
 |
 |
 |
 |
 |
 |
| 10 May - 16 May |
 |
Complete keying & security; devise temporary access paths to SC locations; move 341 materials (5/14-5/17) |
GLE networking upgrades |
Meyer networking upgrades |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 17 May - 23 May |
 |
GLW staff moves: SC (#1 Kimball, Hinman, McDonald, Mustain, 3rd sort, 341 flat cases; #2 Timby & materials; #3 Fischback, Auerbach, Whidden, White); Saroyan Room |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 24 May - 30 May |
 |
Begin GLE 2 cage/sort move |
Fix GLE 341, 331D, HASRC Proc. |
 |
Move rest of Preservation to Wilbur |
 |
 |
 |
 |
 |
 |
 |
 |
| 31 May - 6 June |
 |
GLW staff moves: DO (6/2-6/3?); SC: (Bousman, Steinberg), HASRC, SSRC (6/4-6/5?); Nicolayev & Kerns to Meyer 3; complete GLE 2 cage/sort moves |
Move Ms. Proc. to GLE 3 (6/1); project to create new Stack Staff offices & sort in GLE LL (staff move to follow when best for operations) |
 |
Reconfigure remainder of Galvez for HighWire growth |
 |
 |
 |
 |
 |
 |
 |
 |
| 7 June - 13 June |
 |
Begin installation of exhibit cases |
 |
Fix Meyer 3 for summer inhabitants |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 14 June - 20 June |
 |
 |
Move GLE 1 staff, colls. & ops. to Meyer 1 & 3 |
 |
 |
Close some services; implement GLE summer access point on LL; implement access to GLW ref. materials |
 |
 |
 |
 |
 |
 |
 |
| 21 June - 27 June |
 |
 |
Begin GLE 1 construction; fix GLE 331 A, B, C for HASRG |
Open Summer Services in Meyer |
 |
6/22 - Summer session begins |
 |
 |
 |
 |
 |
 |
 |
| 28 June - July 4 |
 |
Landscaping completed |
Complete GLE shelving installations (added ranges; new microform compact shelving; added oversize cases) |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 5 July - 11 July |
 |
Begin collection moves; Lowood & Trujillo to GLW 2 as soon as offices are complete |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 12 July - 18 July |
 |
ASUL moves into Hopkins Rm. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 19 July - 25 July |
 |
Begin SC public services move (& Armstrong & Noakes to GLW 2); Lowood & Trujillo to GLW 2 as soon as offices ready |
 |
 |
 |
SC closed |
 |
 |
 |
 |
 |
 |
 |
| 26 July - 1 Aug. |
 |
Stat. Consulting from Sweet 4 to GLW 1; complete SC public services move |
 |
 |
 |
SC closed |
 |
 |
 |
 |
 |
 |
 |
| 2 Aug. - 8 Aug. |
 |
OPEN GLW to public |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 9 Aug. - 15 Aug. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 16 Aug. - 22 Aug. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 23 Aug. - 29 Aug. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 30 Aug. - 5 Sept. |
 |
 |
GLE 1 construction complete |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 6 Sept. - 12 Sept. |
 |
 |
Activate GLE 1 |
 |
 |
Close some services (?) |
 |
 |
 |
 |
 |
 |
 |
| 13 Sept. - 19 Sept. |
 |
 |
Open IC/CP & other GLE 1 services |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 20 Sept. - 26 Sept. |
 |
9/21 - major donor event in Bender Rm. |
 |
 |
 |
9/22 - Fall Quarter classes begin |
 |
 |
 |
 |
 |
 |
 |
| 27 Sept. - 3 Oct. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 4 Oct. - 10 Oct. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 11 Oct. - 17 Oct. |
 |
GLW Opening Events |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 18 Oct. - 24 Oct. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| 25 Oct. - 31 Oct. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |